The Habitat for Humanity House

Henry Gonzales is the coordinator for the Knights' construction schedule. If you would like to work at the next build, contact Henry at stalliontheboss@juno.com or telephone 849-6616.

The Fall 2007 house will be built for the Chavez family, shown in the photo below with Henry Gonzales, Sam Szalwinski, and Rudy Escamilla.

The Fall 2007 house will be in the Palo Alto Subdivision in South San Antonio. Take Loop 410 South or Interstate 35 South to Highway 422, the Poteet Jourdanton Fwy. Turn West on Aragon and you will find Palo Alto Subdivision.

If you have never volunteered, there's nothing to it. Anyone can help, including spouses, friends, children (over age 16). There will be an opportunity for supervised teens age 14 and up to help landscape.

Plan to arrive early for the 8 am safety briefing and prayer. Wear appropriate clothing (no open toe shoes), hat, (shorts are okay). Habitats provide safety equipment (gloves, eye protection, helmet) and tools. The Knights provide water, food and snacks.

Volunteers are needed to provide the lunch for the group - usually about 20 people. Typical menus include buckets of chicken, sandwiches, pizza, casseroles, etc. Don't forget the brownies or cookies!

We will clean up about 3 pm and be done by 3:30. It can get hot working outside, and sometimes it rains, but there is always something to be done. There are only 14 workdays. Professionals pour the foundation and do the electrical and plumbing. Volunteers, under the supervision of a professional foreman, do all the rest.

There is a great sense of accomplishment, and you can learn some new skills, so come on down and join us!

  Date Districts Tasks
1 Fri, 9/14 45
Stand, plumb and brace exterior wall panels
Stand interior wall panels
Build front porch beam
Load and install trusses
Prime and paint all exterior trim
2 Sat, 9/15 45
Start installing fascia
Start roof decking
Hang blue board wall sheathing
Snap chalk lines for siding
Install front porch posts
3 Fri, 9/21 Need a District
Install felt paper and drip edge
Install windows  
Start siding
4 Sat, 9/22 41 and 44
Install safety ventilation
Install ceiling insulation dams
Install insulation behind tub & under H2O heater 
Complete siding
5 Fri, 9/28 Leadership Day
Paint exterior siding
Snap lines for shingles
Start roof shingles
Install roof flashing and ridge vent
Start soffit installation
6 Sat, 9/29 32 and 33
Install A/C housing unit
Install window and corner trim on exterior
Caulk and touch up paint exterior trim
Clean interior
7 Fri, 10/5 28
Assemble shed
Install fence posts
Install permanent locksets on exterior doors
Install storm door
8 Sat, 10/6 33 and 34
Install house numbers
Paint interior trimwork
Pre-landscape
9 Fri, 10/12 30 and ?
Paint walls, ceilings, doors and trim
Floor prep
Clean up site
10 Sat, 10/13 26 and 42
Install floor tile
Assemble cabinets
Install cabinets
Paint 2nd coat on doors, trim and base
11 Fri, 10/19 37 and ?
Install interior doors and trim
Install baseboard, window sills and other trim
Install wire shelving
Install interior hardware
12 Sat, 10/20 35 and 38
Caulk and touch up paint interior trim
Start final punch list
Clean house
13 Sat, 10/27 31 and ?
Install fence fabric
Complete any and all remaining tasks
Clean house
14 Sat, 11/3   Landscape

 

 